GOCE Launch Delayed: Replacement Needed for Successful Mission

The correction of the problem will require the replacement of this unit. In order to perform this operation, it will be necessary to de-mate the launcher's upper composite and transport it from the launch pad back to the integration room.

Once in the clean room, the protective fairing that shelters the satellite will be opened and the spacecraft and its adaptor system will be dismounted in order to allow access to the Breeze KM equipment to be replaced.

Taking into account the duration of the refurbishment operations and the re-mating of the adaptor system, satellite and fairing, the launch has been currently rescheduled for 5 October at the same time (16:21 CEST). The satellite and its mission will not be affected by this launch delay.