The correction of the problem will require the replacement of this unit. In order to perform this operation, it will be necessary to de-mate the launcher's upper composite and transport it from the launch pad back to the integration room.
Once in the clean room, the protective fairing that shelters the satellite will be opened and the spacecraft and its adaptor system will be dismounted in order to allow access to the Breeze KM equipment to be replaced.
Taking into account the duration of the refurbishment operations and the re-mating of the adaptor system, satellite and fairing, the launch has been currently rescheduled for 5 October at the same time (16:21 CEST). The satellite and its mission will not be affected by this launch delay.
Franco Bonacina | Source: alphagalileo
Further information: www.esa.int/SPECIALS/GOCE/SEMAC1P4KKF_0.html
Further Reports about: GOCE > GOCE satellite > navigation subsystem
More articles from
Physics and Astronomy:
Lunar Rock-Like Material May Someday House Moon Colonies
06.01.2009 | Virginia Tech (Virginia Polytechnic Institute and State University)
Astrophysicist Helps Map the Milky Way’s Four Spiral Arms
06.01.2009 | Iowa State University
Key to future medical breakthroughs is systems biology
06.01.2009 | Life Sciences
New infant formula safety advice could prevent infant suffering
06.01.2009 | Studies and Analyses
Nicotine Gum Effective for Gradual Smoking Reduction and Cessation
06.01.2009 | Health and Medicine
Annual Congress European Association of Urology: highlights in Stockholm
18.12.2008 | Event News
PRACE hosts First Scientific Conference
16.12.2008 | Event News
USM Conference Explores Issues And Challenges In The Global Construction Sector
10.12.2008 | Event News