Forum for Science, Industry and Business

Sponsored by:     3M 
Search our Site:

 

Antarctica: Neumayer Station III successfully raised

05.02.2010
Hydraulic lifting devices prevent Neumayer Station III from sinking in the ice.

The snow and ice surface in the Antarctic grows continuously so the research station has to be raised annually. The construction concept and technology prove effective right from the beginning.

Nearly double the amount of fresh snow compared to previous Antarctic winters fell on Neumayer Station III during the polar winter of 2009. "Because of the unusually heavy snowfall the station building had to be raised three times in succession with the hydraulic system," says Dr. Eberhard Kohlberg, Logistics Coordinator at the research station of the Alfred Wegener Institute for Polar and Marine Research in the Helmholtz Association since December 2009.

To reach the planned level, the station has undergone two lifting operations since November during which it was raised a metre out of the snow in each case. The third and for this season last lifting operation is now being completed.

By means of the hydraulic system, the technicians raise the legs of the station during each operation. Then new snow is placed underneath and the steel legs are lowered again (see infobox). The process is demanding since the snow piles have to provide stable support for the tons of building load after only a short time. Normal operation continues at the same time without any restrictions. The residents of the Antarctic station merely notice a slight vibration, telling them that the hydraulic legs are currently in motion.

In future, too, the station will be raised every year in summer so that the masses of snow from the previous winter do not hinder research work. The prerequisites for this are a good weather forecast and far-sighted planning. A low wind speed is necessary to ensure that the overall structure of the building is not subjected to strong sideways pressure. "Fortunately there were enough windows of suitable weather this summer," states Dr. Hartwig Gernandt, Project Manager in the Logistics Department at Alfred Wegener Institute. "The mission was accomplished with great success. Everything was running routinely during the second and third lifting operation."

INFOBOX - Raising Neumayer-Station III

The engineers of the Alfred Wegener Institute who work at the station during the Antarctic summer are responsible for lifting the station building.

At the control centre in the so-called hydraulics container, station level U1, a specially developed software controls the hydraulic cylinders - bipods - in the 16 supports: they bear the station building weighing around 2,600 t. The complete lifting process consists of two operations:

1. During the actual lifting process all 16 bipods are extended by the lifting height of about 1.20 metres. The operation takes approx. two hours. Now the entire building is at an elevated position.

2. The foundations now have to be raised in pairs so that fresh snow can be placed underneath. The foundation plates cannot be set down so that the load is carried by the freshly filled snow, until the latter has hardened.

Under favourable weather conditions the entire process takes about 14 days and comprises the following steps:

- Lifting the building by extending all 16 bipods. Cable and pipe connections that go from the building to the ground have to be detached or loosened beforehand.

- Lifting the foundation plates in pairs using the bipod cylinders.

- The engineers fill new snow under the raised foundation plates by means of tracked vehicles with pusher blade and snow blower. Manual shovelling is necessary for the finishing touches so as to guarantee even distribution of the snow.

- The freshly filled snow now has to harden. The foundation plates are slowly and gradually lowered onto the snow piles. Initially the snow gives way under the load. This settling of the snow foundation has to be checked very carefully. Full loading can only take place when settling drops below a certain limit value, which is reached after about 24 hours. Now the crystalline structure of the snow is stable enough to absorb the heavy load.

- Once all 16 bipod supports have been underpinned in this way, the entire garage is filled with snow up to the now higher level. This marks the end of the lifting process. If necessary, the station building can now be raised once again.

The Alfred Wegener Institute conducts research in the Arctic, Antarctic and oceans of the temperate latitudes. It coordinates polar research in Germany and provides major infrastructure to the international scientific community, such as the Polarstern research icebreaker and stations in the Arctic and Antarctic. The Alfred Wegener Institute is one of the sixteen research centres of the Helmholtz Association, the largest scientific organisation in Germany.

Margarete Pauls | idw
Further information:
http://www.awi.de

More articles from Architecture and Construction:

nachricht Designing Architecture with Solar Building Envelopes
16.01.2017 | Fraunhofer-Institut für Solare Energiesysteme ISE

nachricht How to inflate a hardened concrete shell with a weight of 80 t
11.01.2017 | Technische Universität Wien

All articles from Architecture and Construction >>>

The most recent press releases about innovation >>>

Die letzten 5 Focus-News des innovations-reports im Überblick:

Im Focus: Designing Architecture with Solar Building Envelopes

Among the general public, solar thermal energy is currently associated with dark blue, rectangular collectors on building roofs. Technologies are needed for aesthetically high quality architecture which offer the architect more room for manoeuvre when it comes to low- and plus-energy buildings. With the “ArKol” project, researchers at Fraunhofer ISE together with partners are currently developing two façade collectors for solar thermal energy generation, which permit a high degree of design flexibility: a strip collector for opaque façade sections and a solar thermal blind for transparent sections. The current state of the two developments will be presented at the BAU 2017 trade fair.

As part of the “ArKol – development of architecturally highly integrated façade collectors with heat pipes” project, Fraunhofer ISE together with its partners...

Im Focus: How to inflate a hardened concrete shell with a weight of 80 t

At TU Wien, an alternative for resource intensive formwork for the construction of concrete domes was developed. It is now used in a test dome for the Austrian Federal Railways Infrastructure (ÖBB Infrastruktur).

Concrete shells are efficient structures, but not very resource efficient. The formwork for the construction of concrete domes alone requires a high amount of...

Im Focus: Bacterial Pac Man molecule snaps at sugar

Many pathogens use certain sugar compounds from their host to help conceal themselves against the immune system. Scientists at the University of Bonn have now, in cooperation with researchers at the University of York in the United Kingdom, analyzed the dynamics of a bacterial molecule that is involved in this process. They demonstrate that the protein grabs onto the sugar molecule with a Pac Man-like chewing motion and holds it until it can be used. Their results could help design therapeutics that could make the protein poorer at grabbing and holding and hence compromise the pathogen in the host. The study has now been published in “Biophysical Journal”.

The cells of the mouth, nose and intestinal mucosa produce large quantities of a chemical called sialic acid. Many bacteria possess a special transport system...

Im Focus: Newly proposed reference datasets improve weather satellite data quality

UMD, NOAA collaboration demonstrates suitability of in-orbit datasets for weather satellite calibration

"Traffic and weather, together on the hour!" blasts your local radio station, while your smartphone knows the weather halfway across the world. A network of...

Im Focus: Repairing defects in fiber-reinforced plastics more efficiently

Fiber-reinforced plastics (FRP) are frequently used in the aeronautic and automobile industry. However, the repair of workpieces made of these composite materials is often less profitable than exchanging the part. In order to increase the lifetime of FRP parts and to make them more eco-efficient, the Laser Zentrum Hannover e.V. (LZH) and the Apodius GmbH want to combine a new measuring device for fiber layer orientation with an innovative laser-based repair process.

Defects in FRP pieces may be production or operation-related. Whether or not repair is cost-effective depends on the geometry of the defective area, the tools...

All Focus news of the innovation-report >>>

Anzeige

Anzeige

Event News

12V, 48V, high-voltage – trends in E/E automotive architecture

10.01.2017 | Event News

2nd Conference on Non-Textual Information on 10 and 11 May 2017 in Hannover

09.01.2017 | Event News

Nothing will happen without batteries making it happen!

05.01.2017 | Event News

 
Latest News

Multiregional brain on a chip

16.01.2017 | Power and Electrical Engineering

New technology enables 5-D imaging in live animals, humans

16.01.2017 | Information Technology

Researchers develop environmentally friendly soy air filter

16.01.2017 | Power and Electrical Engineering

VideoLinks
B2B-VideoLinks
More VideoLinks >>>